When is a Sprint considered to be over?

  1. When all tasks are complete

  2. When the team decides

  3. When the timebox expires

  4. When a review meeting is held

The correct answer is: When the timebox expires

A Sprint is considered to be over when the timebox expires, which is a core principle of Scrum methodology. Each Sprint is fixed in duration, typically lasting between one to four weeks, and is designed to create a consistent rhythm for the Scrum Team. This time constraint emphasizes time management and focused effort; thus, a Sprint cannot be extended based on task completion. The expiration of the timebox marks the end of the Sprint regardless of whether all tasks or user stories are finished. This approach helps teams avoid scope creep and encourages them to prioritize what is achievable within the Sprint timeframe. Additionally, it ensures that the rhythm of regular feedback and inspection is maintained through sprint reviews and retrospectives, allowing the team to reflect and adapt for the next Sprint. Other options, such as when all tasks are complete or when the team decides, do not align with the framework’s emphasis on strict timeboxes, which is crucial for maintaining predictability and efficiency in the Agile process. Holding a review meeting does not signify the end of the Sprint either; rather, it is a part of the Sprint culmination that takes place once the timebox has expired.