Which event allows the Scrum Team to discuss what went well and what could be improved?

  1. Daily Scrum

  2. Sprint Review

  3. Sprint Retrospective

  4. Sprint Planning

The correct answer is: Sprint Retrospective

The event that allows the Scrum Team to discuss what went well and what could be improved is the Sprint Retrospective. This meeting is specifically designed to reflect on the past Sprint and focuses on the team’s processes, collaboration, and any challenges faced during the work cycle. The primary goal is continuous improvement; the team identifies successes to leverage and areas where they can enhance their performance in future Sprints. During the Sprint Retrospective, the team assesses outcomes and feedback from the previous Sprint in a safe environment, which encourages open communication. It fosters a culture where team members can share their thoughts, suggest improvements, and establish actionable steps to implement in the next iteration. This self-reflective practice is integral to the Scrum framework, emphasizing learning and adaptation. In contrast, other events like Daily Scrum centers around daily progress and immediate obstacles, the Sprint Review focuses on the product being delivered and stakeholder feedback, while Sprint Planning is about defining work to be accomplished in the upcoming Sprint. These events serve distinct purposes not centered on the team's retrospective analysis and process improvements.