Which Scrum event includes feedback from stakeholders about what was accomplished in the Sprint?
Daily Scrum
Sprint Review
Sprint Retrospective
Sprint Planning
The correct answer is: Sprint Review
The Sprint Review is the Scrum event designed specifically for gathering feedback from stakeholders about the work that was completed during the Sprint. During this event, the Scrum team presents the increment of work that has been completed, demonstrating how the product has evolved. Stakeholders, including customers, users, and other interested parties, have the opportunity to inspect the increment and provide their insights, which helps inform the next steps in product development. This collaborative feedback process is essential for ensuring that the product aligns with stakeholder expectations and needs, allowing for adjustments in priorities or enhancements for future Sprints. The focus on stakeholder feedback distinguishes the Sprint Review from other Scrum events, such as the Daily Scrum, Sprint Retrospective, and Sprint Planning, which have different objectives.